Estimated Completion Time

Time estimated to finish a job. The job is complete when total net pieces for the job equals the pieces required. The estimated completion time is computed using the shift schedule and hours to go to determine the estimated date and time the job will end.

If the shift schedule does not include any idle period, the estimated completion time would be:

·Estimated Completion Time = Current Date and Time + Hours to Go  

If the shift schedule does include idle periods, the estimated completion time would be:

·Estimated Completion Time = Current Time + Hours to Go + Scheduled Idle Time