Hours to Go

Total hours and minutes estimated to finish a job. The job is complete when total net pieces for the job equals the pieces required. Before 5% of the pieces required have been made, Hours to Go is calculated as follows:

Hours to Go = Remaining Setup Time + ((Pieces to Go) / (Standard Rate))

After 5% of the pieces required have been made, the following formula is used:

Hours to Go = (Pieces to Go) / (Actual Rate)

For maintenance jobs, Hours to Go is equal to the actual setup time remaining.

NOTE: If the job scheduled is a family job, the Hours to go indicates the expected run time of the longest running child job.